Installation and maintenance 

1. Installing
When installing the Green Toilet 330, make sure that the shaft and sitting level and the ventilation tube can be lifted up for change of the tank. Also the liquid hose must be taken into account.
2. Implementation
A layer of 5 to 6 cm of covering material must be placed in the tank before use. This needs to be done also after the emptying of the tank.
3. The use
After use, one scoop of covering material must be added. Composting process should be facilitated by stirring from the toilet seat weekly. At the same time the leavings may be leveled and accelerator to the compost added.

 

4. Emptying 
The tank is easy to empty: after the sitting shaft and the ventilation tube are lifted up and the liquid tube is removed, the tank may be emptied. When spare tanks are used, the full tank is first replaced, then fitted with a valve and covering board and the insides are left to compost.

 

5. Liquid treatment
Green Toilet has a unique liquid treatment. The most of the liquids evaporates through the ventilation. During the heavy use the liquids are lead to tank, to soil treatment or to bio-filter. Also a separate urinal can be installed, in places where the use is high.

 

6. The use of compost
After the leavings have composted enough they should be after-composted in a pile on the ground or in wooden frame..

 